Classroom Renovation

Project Status

Design is in progress and is scheduled to be submitted to DSA Fall 2007 and anticipated to be received back Spring 2008. Following approval from DSA and the bidding process, construction scheduled to start Fall 2008.

Design is in progress.

Project Title: Reedley College Modernization Projects

Funding Source: Measure E - $15,262,000

Project Description:

  • Classrooms/Offices Modernization
  • Student Center Modernization
  • Bookstore Modernization
  • Health/Fitness Modernization
  • Ag Canopy

The scope of each of the projects has not been determined.

Anticipated Completion Date: 2008

Status: There have been ongoing meetings between Phillips Metsch Sweeney Moore Architects and the college regarding master planning and design criteria for identification of project components and scope. As was previously presented to the Bond Oversight Committee, the Board approved at the April 2006 Board Meeting amendments to the District’s Measure E Bond implementation plan that include the modernization of the existing bookstore.

Estimated Project Budget: Budget for master planning is $50,000. Budgets will be defined when project scopes have been established.

Project Title: Reedley College Modernization Projects

Funding Source: Measure E - $15,262,000

Project Description:

  • Classrooms/Offices Modernization
  • Student Center Modernization
  • Bookstore Modernization
  • Health/Fitness Modernization

The scope of each of the projects has not been determined.

Anticipated Completion Date: 2008

Status: There have been ongoing meetings between Phillips Metsch Sweeney Moore Architects and the college regarding master planning and design criteria for identification of project components and scope. As was previously presented to the Bond Oversight Committee, the Board approved at the April 2006 Board Meeting amendments to the District’s Measure E Bond implementation plan that include the modernization of the existing bookstore.

Estimated Project Budget: Budget for master planning is $50,000. Budgets will be defined when project scopes have been established.

Funding Source: Measure E - $15,262,000

Project Description:

  • Classrooms/Offices Modernization
  • Student Center Modernization
  • Bookstore Modernization
  • Health/Fitness Modernization

The scope of each of the projects has not been determined.

Anticipated Completion Date: 2008

Status: The Board approved Phillips Metsch Sweeney Moore Architects as the project architect at the September 6, 2005 meeting. District held initial kick-off meeting with PMSM on October 6, 2005.

Funding Source: Measure E

Project Description: The project will modernize 40 to 50-year old classrooms to include heating, air conditioning, ventilation, plumbing, communications and electrical systems.

Anticipated Completion Date: 2008

Status: District has received qualified responses from architects and will review and make a selection of a design team Fall 2005.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 602,966 0 70,000 0 0 0
Consultant Services 180,890 0 10,000 0 0 0
Fees & Other Charges 108,112 0 0 0 0 0
Construction & Equipment 6,029,660 0 0 0 0 0
Inspection & Testing 144,297 0 0 0 0 0
Contingency 422,075 0 0 0 0 0
Total 7,488,000 0 80,000 0 0 0

District has received qualified responses from architects and will review and make a selection of a design team Spring 2005.

District has received qualified responses from architects and will review and make a selection of a design team Spring 2005.