Coronavirus Resources District information pertaining to Coronavirus (COVID-19)

New Instructional Classrooms

Project Status

Project Completed
(will not be shown on future Bond Oversight Committee Status Reports)

Project Title: Reedley College Classroom Addition

Funding Source: Measure E

Project Description: The Classroom Addition will add 11,737 sq. ft. of new building housing (8) offices, (8) classrooms, restrooms, conference room, meeting room, resource and AVTV support.

Anticipated Completion Date: Summer 2006

Status: Building is in use and site work is being completed.

Estimated Project Budget: Prepared by Phillips Metsch Sweeney Moore Architects

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 312,122 274,122 38,000 30,240 7,752 304,362
Consultant Services 96,340 12,090 81,660 16,012 0 28,102
Fees & Other Charges 85,014 34,760 50,254 0 0 34,760
Construction & Equipment 3,323,323 647,639 2,675,684 2,060,223 615,461 2,707,862
Inspection & Testing 108,780 14,944 93,836 75,458 0 90,402
Contingency 150,776 0 150,776 0 0 0
Total 4,076,355 983,555 3,090210 2,181,933 623,213 3,165,488

Project Title: Reedley College Classroom Addition

Funding Source: Measure E

Project Description: The Classroom Addition will add 11,737 sq. ft. of new building housing (8) offices, (8) classrooms, restrooms, conference room, meeting room, resource and AVTV support.

Anticipated Completion Date: Spring 2006

Status: Construction is in progress.

Estimated Project Budget: Prepared by Phillips Metsch Sweeney Moore Architects

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 312,122 274,122 38,000 30,240 7,752 304,362
Consultant Services 96,340 12,090 81,660 16,102 0 28,102
Fees & Other Charges 85,104 34,760 50,254 0 0 34,760
Construction & Equipment 3,323,323 647,639 2,675,684 2,060,223 615,461 2,707,862
Inspection & Testing 108,780 14,944 93,836 75,458 0 90,402
Contingency 150,776 0 150,776 0 0 0
Total 4,076,355 983,555 3,090,210 2,181,933 623.213 3,165,488

Funding Source: Measure E

Project Description: The Classroom Addition will add 11,737 sq. ft. of new building housing (8) offices, (8) classrooms, restrooms, conference room, meeting room, resource and AVTV support.

Anticipated Completion Date: Spring 2006

Status: Construction is in progress.

Estimated Project Budget: Prepared by Phillips Metsch Sweeney Moore Architects

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 286,020 260,238 25,782 7,680 18,102 267,918
Consultant Services 95,340 13,680 81,660 2,860 73,050 16,540
Fees & Other Charges 90,615 50,146 40,469 0 0 50,146
Construction & Equipment 3,336,700 647,639 2,689,061 436,713 2,107,647 1,084,335
Inspection & Testing 108,780 11,511 97,269 13,867 62,600 25,378
Contingency 158,900 0 158,900 0 0 0
Total 4,076,355 983,214 3,093,141 461,120 2,261,399 1,444,334

Funding Source: Measure E

Project Description: The Classroom Addition will add 11,737 sq. ft. of new building housing (8) offices, (8) classrooms, restrooms, conference room, meeting room, resource and AVTV support.

Anticipated Completion Date: 2005

Status: Construction in progress.

Estimated Project Budget: Prepared by Phillips Metsch Sweeney Moore Architects

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 286,020 260,238 25,782 0 0 260,238
Consultant Services 95,340 13,680 81,660 0 0 13,680
Fees & Other Charges 90,615 50,146 40,469 0 0 50,146
Construction & Equipment 3,336,700 647,639 2,689,061 0 0 647,639
Inspection & Testing 108,780 11,511 97,269 0 0 11,511
Contingency 158,900 0 158,900 0 0 0
Total 4,076,355 983,214 3,093,141 0 0 983,214

Project was awarded January 2005. Notice to Proceed issued February 2005. Construction is in progress.

DSA approval received October 6, 2004. The project is out to bid with a bid date of January 18, 2005. Construction anticipated to start Spring 2005.

The project was presented to the Board for their review in February. The District is continuing to develop specific design criteria and construction documents for submission to DSA.

The District has held initial planning and design development meetings with the architect to develop educational specifications, design criteria and design schematics. Design schematics have been completed and presented to the Board.

The SCCCD Board of Trustees at its June 24 meeting selected and authorized the administration to enter into an agreement with Phillips Metsch Sweeney Moore Architects as the project architect. The District has held initial planning and design development meetings with the architect to develop educational specifications and preliminary design criteria.