Coronavirus Resources District information pertaining to Coronavirus (COVID-19)

Gymnasium Renovation

Project Status

FCC Gymnasium Modernization (Practice Court)
Measure E Budget: $4,040,205
Total Expenses to Date: $3,177,273
Balance: $862,932

Construction is substantially complete with punchlist work in progress. This project will be accepted at the August 2007 Board Meeting. Final invoices are being received and processed, with the expectation that the final balance of the project will be reduced to zero.

Construction is in progress.

Construction is in progress.

Project Title: FCC Gymnasium Modernization

Funding Source: Measure E

Project Description: Construction, renovation and modernization of physical education facilities and the modernization of heating, ventilation and cooling system.

Anticipated Completion Date: Fall/Winter 2007

Status: Project was awarded at the May 2, 2006 Board Meeting and construction began June 2006.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 325,656 81,477 169,000 156,762 12,000 238,239
Consultant Services 126,101 9,969 20,000 14,311 5,689 24,280
Fees & Other Charges 64,448 5,100 22,000 21,675 0 26,775
Construction & Equipment 3,184,000 0 232,000 59,868 172,132 59,868
Inspection & Testing 180,000 2,700 7,500 3,750 0 6,450
Contingecy 170,000 0 0 0 0 0
Total 4,040,205 99,246 450,500 256,366 189,821 355,612

Project Title: FCC Gymnasium Modernization

Funding Source: Measure E

Project Description: Construction, renovation and modernization of physical education facilities and the modernization of heating, ventilation and cooling system.

Anticipated Completion Date: Fall/Winter 2007

Status: Project bids April 2006 and will be taken to the Board for award May 2006.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 298,063 81,477 216,586 138,576 12,000 220,053
Consultant Services 89,419 9,969 50,000 7,927 4,000 17,896
Fees & Other Charges 53,442 5,100 20,000 18,634 0 23,734
Construction & Equipment 2,980,626 0 80,000 0 0 0
Inspection & Testing 113,806 2,700 17,000 0 0 2,700
Contingecy 208,644 0 0 0 0 0
Total 3,744,000 99,246 383,586 165,137 16,000 264,383

Funding Source: Measure E

Project Description: Construction, renovation and modernization of physical education facilities and the modernization of heating, ventilation and cooling system.

Anticipated Completion Date: Fall/Winter 2007

Status: BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 298,063 66,900 220,000 61,886 147,410 128,786
Consultant Services 89,419 9,969 50,000 1,595 46,582 11,564
Fees & Other Charges 53,442 5,100 20,000 15,507 0 20,607
Construction & Equipment 2,980,626 0 80,000 0 0 0
Inspection & Testing 113,806 2,200 17,000 0 0 2,200
Contingecy 208,644 0 0 0 0 0
Total 3,744,000 84,169 387,000 78,988 193,992 163,157

Funding Source: Measure E

Project Description: Construction, renovation and modernization of physical education facilities and the modernization of heating, ventilation and cooling system.

Anticipated Completion Date: 2007

Status: BCA Architects has conducting preliminary meetings with District to develop schematic design.BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 298,063 66,900 100,000 0 0 66,900
Consultant Services 89,419 9,969 25,000 0 0 9,969
Fees & Other Charges 53,442 5,100 10,000 0 0 5,100
Construction & Equipment 2,980,626 0 80,000 0 0 0
Inspection & Testing 113,806 2,200 17,000 0 0 2,200
Contingecy 208,644 0 0 0 0 0
Total 3,744,000 84,169 232,000 0 0 84,169

BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA will submit schematic design to Office of State Architect for preliminary review and comments regarding access compliance by May 2005. BCA and the District will then proceed with programming and design development.

Architect approval by Board is scheduled for January 11, 2005. Programming and schematic design will begin Spring semester of 2005.